Market and projectsDeadline 10/27/2026
Azuer I battery module (6 MW) out for comment, to hybridise the Azuer I solar plant (Manzanares)
The Industry and Energy Area of the Government Delegation in Castilla-La Mancha has opened public consultation on the prior administrative and construction authorisation of the BESS Azuer I battery module, 6 MW installed and 12 MWh of capacity after power limitation, to hybridise the existing Azuer I solar plant (49.98 MW) in Manzanares. The project includes the buried 30 kV line to the Azuer 30/220 kV substation, where Azuer I and Azuer II evacuate, with the substation upgraded for joint export. The promoter is Calatrava Solar I and the comment term is fifteen days from publication (file PFot-ALM-158).
BESSSolarManzanares· Ciudad Real