Public consultation on the 1.6 MW PS Palaudàries self-consumption solar plant (Barcelona)

The Direcció General d'Energia of the Generalitat de Catalunya has opened public consultation on Delta Renovables' application for prior and construction authorisation, a specific public-utility declaration, approval of the specific public-interest action on non-developable land and environmental impact assessment for the «PS Palaudàries» ground-mounted self-consumption solar plant, 1,600 kW, in Lliçà de Vall. For a self-consumption plant of this size the application takes the full route — public utility plus a specific public-interest action on non-developable land. Submissions are due within 15 days from publication.

SolarLliçà de Vall· Barcelona