Market and projectsDeadline 11/19/2026
Public utility of the three Zednemen solar plants (261 MW) opens for comment
The Industry and Energy Area of the Government Delegation in Castilla-La Mancha has opened public information on the request for a public-utility declaration covering the Zednemen (61.61 MW), Zednemen Fase II (143.01 MW) and Zednemen Fase III (56.43 MW) solar plants and their evacuation infrastructure, promoted by Energías Renovables Zednemen (files PFot-593, PFot-594 and PFot-596). The three are handled in a single application and share evacuation, and they affect Casarrubios del Monte (Toledo) and Fuenlabrada and Alcorcón (Madrid). All three already hold prior and construction authorisations. Comments run for thirty days from the day after publication, working days under Law 39/2015 (earliest close, 19 November).
SolarCasarrubios del Monte· ToledoFuenlabrada· MadridAlcorcón· Madrid