Capacity expansion authorised at the Añover de Tajo substation, 132/45/15 kV and 60 MVA

Castilla-La Mancha's energy transition directorate grants prior and construction authorisation for the capacity expansion of the Añover de Tajo substation, 132/45/15 kV and 60 MVA, in Añover de Tajo (Toledo), requested by UFD Distribución Electricidad (reference 2401/00085). A power expansion at a 132 kV substation changes the capacity available at that point of the distribution network, which is where plants too small for the transmission grid connect.