400 kV in/out bay at the Moreruela substation authorised in Zamora, with public utility
The Dirección General de Política Energética y Minas has granted Red Eléctrica de España prior administrative authorisation and construction authorisation for the 400 kV double-circuit overhead transmission line forming an in/out bay at the Moreruela substation off the 400 kV Grijota-Villarino 2 line, in Moreruela de los Infanzones, and has declared it to be of specific public utility. The public-utility declaration is the act that opens the way to expropriating the affected land: for anyone looking for a connection point in north-west Zamora, this bay changes the 400 kV mesh that local access depends on.
SolarWindBESSData CenterMoreruela de los Infanzones· Zamora