Mulhacén storage module (21.56 MW) authorised to hybridise with the Mulhacén Solar plant, Esquivias
Spain's Directorate-General for Energy Policy and Mines has granted Mulhacen Solar, SLU prior administrative authorisation for the 21.56 MW Mulhacen energy storage module and its evacuation infrastructure, to be hybridised with the 70 MW Mulhacen Solar PV plant in Esquivias (Toledo). The file is processed by the State. For a developer this is the route to add batteries to a PV plant on its own connection point, without bidding for new access capacity.