Canary Islands clears the 66 kV Santa Águeda-El Tablero 2 transmission line on Gran Canaria
Decree 143/2026 approves execution of the 66 kV single-circuit overhead/underground transmission line Santa Águeda-El Tablero 2, on the island of Gran Canaria, promoted by Red Eléctrica de España, and orders the amendment of the affected planning instruments. This is island transmission network: every new 66 kV axis reshapes where a project can request access on the island. File AT23-015.
SolarWindOffshore WindBESSData CenterLas Palmas· Canarias