Geovian
Back to Radar
Market and projectsDeadline 10/21/2026

Coalsema: consultation opens on hybridising a cogeneration plant with solar and batteries (Berantevilla)

Álava's territorial delegation has opened public consultation on the prior and construction authorisations for «Coalsema», by Compañía Alavesa de Secado de Madera, which hybridises its existing cogeneration unit with a solar park and storage at Berantevilla. It covers 13,284 modules of 715 Wp and 26 inverters of 320 kVA (8,320 kVAn), seven battery containers of 1,629.4 kWh rated 5,600 kW, and two transformer centres. The purpose is self-consumption with surplus export and the connection point is the internal network. Submissions run for 20 working days from publication.

SolarBESSBerantevilla· Álava