Prior authorisation refused for the 125 MW Satrebares wind farm in Lugo and A Coruña

The Directorate-General for Energy Policy and Mines has refused Maracaibo Solar, S.L.'s application for prior administrative authorisation of the 125 MW «Satrebares» wind farm and its 220 kV evacuation infrastructure, and has closed file SGIISE/PEol-910. The refusal rests on the unfavourable environmental impact statement of 31 March 2026. The project had obtained transmission grid access at Red Eléctrica's Abegondo 220 kV substation, which matters to anyone tracking how that node is taken up.