Market and projects
PBAT Millor Storage battery project (1.68 MW) sent to full environmental assessment
The environmental impact report on the PBAT Millor Storage project, in Sant Llorenç des Cardassar, rules that it must go through full (ordinary) environmental impact assessment because significant effects are foreseen. It is a stand-alone battery plant of 1.678 MW and 10.068 MWh, six hours of duration, on plots 476 and 511 of polygon 2, evacuating through a 0.88 km underground 15 kV line to the Millor substation via E-Distribución's network. The promoter intends to hybridise it later with a 1.554 MW solar plant on the same land. The ordinary route adds an environmental impact study and a public consultation of at least thirty days.
BESSSant Llorenç des Cardassar· Illes Balears