Market and projectsDeadline 12/2/2026
Public consultation on Eclipse Solar, a 99.9 MW PV plant across five Burgos municipalities
The Industry and Energy Office of the Government Subdelegation in Burgos has opened public consultation on the environmental impact statement and prior administrative authorisation of the 99.935 MW «Eclipse Solar» PV plant, promoted by Solaria Promoción y Desarrollo Fotovoltaico, in Briviesca, Grisaleña, Berzosa de Bureba, Zuñeda and Fuentebureba (file PFot-1229). Its evacuation starts with 30 kV underground lines to the plant substation. Comments are due within forty-five (45) days from the day after publication: if you hold land or a project nearby, confirm the exact closing date with the authority.
SolarBriviesca· BurgosGrisaleña· BurgosBerzosa de Bureba· BurgosZuñeda· BurgosFuentebureba· BurgosBurgos· Castilla y León