Geovian
Back to Radar
Market and projects

Public consultation on the PS_PB BESS Brunyola hybrid: 1,575 kW solar and 990 kW of storage

Catalonia's territory, housing and ecological transition department has opened public consultation on the applications for prior administrative and construction authorisation, specific public-interest use of non-developable land, environmental impact assessment and a public-utility declaration for the PS_PB BESS Brunyola hybrid installation — a 1,575 kW solar plant and a 990 kW storage plant — and its evacuation infrastructure of underground 25 kV lines, in Brunyola i Sant Martí Sapresa (Girona), file FUE-2025-04777585. The file bundles the energy, planning, environmental and public-utility consents into a single procedure, the last of which enables expropriation.

SolarBESSBrunyola i Sant Martí Sapresa· Girona