Public consultation on a 2.4 MW solar plant in San Bartolomé de Tirajana (Gran Canaria)

The Canary Islands' Directorate-General for Energy has opened public consultation on the authorisation application for a 2,400 kW grid-injection solar plant in the municipality of San Bartolomé de Tirajana, on Gran Canaria, promoted by Travesía Capital, SL (file ER250026). With a construction budget of €2.01 million, it evacuates at 20 kV into the CERCADO_ES line of the Arguineguín substation. The notice gives thirty days from publication; the date shown is the earliest the window can close, as the term runs in working days.