Market and projects
Binding report issued on a 5 MW solar plant in the municipality of Cordoba
Cordoba's Delegacion Territorial de Sostenibilidad y Medio Ambiente has published the binding report issued on a 5 MW solar plant with 20 kV evacuation infrastructure, promoted by Benbros PV, SL, in the municipality of Cordoba, within the unified environmental authorisation procedure (file AAU/CO/0036/24S). The binding report is the environmental ruling that conditions that authorisation, so it settles the conditions the project carries into the final decision.
SolarCórdoba· Córdoba