Grid
Red Eléctrica completes the 220 kV Calatorao substation (Zaragoza)
Red Eléctrica has completed construction of the 220 kV Calatorao substation and its coupling to the Jalón-Los Vientos 220 kV line, an €8.8m investment. It is the substation from which the 220 kV line to the «Proyecto Rhodes» data-centre campus in La Almunia de Doña Godina and Alfamén runs, according to the environmental file published in the Aragón gazette. A new 220 kV bay in service changes the map of available connection points in the Jalón valley.
SolarWindBESSData CenterCalatorao· Zaragoza